Barcelona and Turkish construction company Limak have reached an agreement to complete the roof installation at Spotify Camp Nou, with investors approving the final terms and depositing €300m.
The sum represents an increase to the loan approved by Barcelona’s ordinary general assembly on 19 September. The agreement follows months of negotiations and largely preserves the conditions set out in the original contract.
Limak will remain responsible for completing the stadium redevelopment, although other subcontractors may be used during the final phase, as was expected from the outset and had already happened during earlier stages of the project.
Work on the roof is due to begin as soon as the current season ends, although an exact start date has not yet been confirmed. Under the signed agreement, the project is scheduled to be completed during the second half of the 2027-28 season.
The relationship between Barcelona and Limak had experienced tensions over the construction timetable, but the dispute did not lead to a change of contractor. Barcelona had considered that possibility from the beginning as an alternative if contractual obligations were not met.
The investors are satisfied with the revenue already being generated by Spotify Camp Nou, which currently has a capacity of 62,652. The most recent El Clasico in La Liga against Real Madrid produced €19.1m in income, strengthening their belief that the approved plans can deliver the anticipated increase in revenue.
The roof work involves lifting a structure weighing 3,000 tonnes. Alongside that operation, the completion of Barcelona’s new store and museum is regarded as central to the project’s commercial growth.
The final interior work at both facilities is currently under way, and they are expected to be ready to open at the start of 2027. Their launch is expected to provide another increase in the club’s revenues.
Once the roof is complete, Barcelona will be able to return to Spotify Camp Nou with all three tiers of seating open to supporters. The club has reserved Estadi Olimpic Lluis Companys in Montjuic for the 2027-28 season as a precaution.
Current forecasts approved by the investors suggest Barcelona will be able to play the second half of that season at Spotify Camp Nou. The club expects to use Estadi Olimpic Lluis Companys in Montjuic during the first half before returning to its renovated home.
Barcelona had already ruled out reopening the third tier in stages because of the difficulties involved in evacuating supporters and securing the necessary municipal licences. As a result, the entire third tier is expected to open at the same time as the club’s return to Spotify Camp Nou.
The stadium’s double VIP box wing, regarded as the project’s main revenue-generating feature, is scheduled to operate at full capacity during the 2028-29 season. That campaign will conclude with Spotify Camp Nou hosting the Champions League final, 30 years after the stadium last staged the event, when Manchester United played Bayern Munich.